How much steel and concrit required in 1000 square feet
slab?
Answer Posted / swaminathan
Assume Slab Thickness 120 & Steel 80kg/Cum
Steel = .12*1000*80 = 9600 kg = 9.6 MT
Concrete = .12*1000 = 120 Cum
| Is This Answer Correct ? | 12 Yes | 23 No |
Post New Answer View All Answers
Basic questions of civil engineering
What is the Tor steel Consumption for residential building G+24 footing (thum rule) ?
How many lbs are there in a yard?
what is the ingredient value of 40mm and 20mm aggregates?
what is the percentage of silt in black cotton soil.?
what is the permanent solution applied for restoration of leaning tower of pisa?
Describe the role of independent Quantity surveyor?
how many material required for brickbat water proofing of toilets.
What is OSHA compliance?
what post do you prefer to work in this company and why do you think you can serve better in such position?
how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?
Will going from a 3-tap to 6-tap increase water pressure?
what are the types of dimensioning?
what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?
How much river sand contain the 6 & 10 wheeler truck? Or Maximum sand that any type of truck carry?