for one cum 1: 6 cement mortar brickwork
Bricks:- 500 no
Cement:- 15 bags
Sand :- 2.5 cum ( .9 brass)
| Is This Answer Correct ? | 3 Yes | 11 No |
Post New Answer View All Answers
it is a corrected question." make a list of engineering property(properties) of soil.
Why do we not deduct steel volume to find actual volume of concrete in practical as we have studied that,,, actual volume of concrete = volume of column- volume of steel pls explain with reference of IS code?????
What is a hatch patterns?
What is semirigid connections?
how much cement sand n bricks required in im3?and how much in plaster?
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
how to calculate the scour depth
The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it
how to calculate the steel in 500yard
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals
What are the delays in construction projects due to approvals from owners? How can we analyze them in different prospective? Whats their affects and effects on presently going work?
Explain major difference between auto level and dumpy level?
How to Rectify deep crack formed on Brick Wall? Explain the method of rectify the defect?
Define What is the tallest man made structure in the world?