brick work with 1:6 cement mortar how many bricks and
cement and sand require for 1cum
Answer Posted / vijendrasinh
1 cum ratio 1:6
brick - 445 nos + 5 percent add.=500 nos App.
mortar 1 cum .30
cement= (1/7)*0.3=0.0428/.035=1.224 bags
sand= (6/7)*.30=0.26 cum.
| Is This Answer Correct ? | 15 Yes | 2 No |
Post New Answer View All Answers
What is pre-stressed concrete?
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
how much need sand and cement for 1 cft roof construction?
what does the track parameter mean in staad.pro?
Explain what is the release of lien?
How to decide/consider the grade of bitumen for dbm.
how to calculate the material from ratio of work PCC, RRM,POINTING, RCC
HOW TO CLACULATE CEMENT AND SAND CONSUMPTION FOR THE STAIRCASE KOTA FLOORING IN THE RATIO OF 1:4 50 MM THICKNESS
how to calculate the strength of rebound hammer test reading in building construction ?
Why is the statue of liberty made of copper?
How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?
How can i do RCC rate analysis?
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete
Providing and casting in situ cement concrete M-25 of trap/granite/quartzite/gneiss metal for rcc, Providing formwork,Curing the concrete and Complete. what is rate per Cum. and what is rate for M-30 Grade Concrete.