what is the weight of 8mm dia steel with 1 meter length.
Is there any formula to calculate the weight for any given
diameter
Answer Posted / k.paul lessley valavan
Rebar Weight Formula?
Exmaple:-
There is another way of calculating the specific weight (or unit weight) of a rebar. Especially for those who are interested of rebars less than 10mm of dia.
the way is to calculate it mathematically knowing that the
Note:-
a.] Density of steel rebars is 7851 Kg/m3.
b.] 8mm Diameter Rebar
A.] Formula:-
Unit weight [Kg/m] = Cross-Sectional Area [m2] x Density [kg/m3]
B.] Answer:-
Unit weight [Kg/m] = (22/7)x(radius)2 x 7851 kg/m3
Unit weight [Kg/m] = 3.14 x 16 x 7851 kg/m3
Unit weight = 0.395 Kg/m
8mm dia 1m weight = 0.395kg
Weight of Rebar = .0395[Kg/m] x Rebar length
8mm dia 3.66m length Rebar Weight ?
= .0395[Kg/m]x 3.66 [m]
= .14457[Kg]
| Is This Answer Correct ? | 6 Yes | 2 No |
Post New Answer View All Answers
What is the Systematic Responsibility Site Engineer? Who are the above and under co-oridinating ? What is office & Site co-ordination of Site Engineer?
What is the significance of cost estimate knowledge for an architect?
What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet
What are the steps involved in the concreting process?
Why are pull-out tests performed for soil nails?
what is the water-cement ratio of mix design while 30mpa in 7 days?
Any strength is a stress but any stress is not strength
To pcc 11 ft x 24 ft .How many bags of cement, sand and aggregate required? And for roofing how many cgi sheets required?
List out some of the common problems that architect have to tackle it?
Why are separation membranes used between concrete pavement slab and sub-base?
Volume of 25kg putty bag & 40 kg putty bag volume??
How can explode a block?
I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations
what would be the design load of R.C.C Cooling tower per cell.?
For plate load test why we are applying pressure 3 times the proposed allowable bearing pressure? Is there any supporting standards for this?