Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

What is the difference between time ticket and time event
confirmation and when they are used ?

Answer Posted / krish

In my understanding CO11N, is generally used to confirm the
production execution at operation level or sub operation
level or


normally for milestone operation confirmation.Automatic
Goos movement can also be performed when this T Code is
executed.


There is no track of exact setup start time,end
time,execution start time and end time.


Using CO19,we can track the or post the exact or actual
setup start time,setup end time,processing start time,end
time for each


operation.


More related to Time Eevnt confirmation,


Time Event Confirmations


Every confirmed time event is assigned internally to a
record type group:


Setup times are assigned to record type group 1.


Processing times are assigned to record type group 2.


Teardown times are assigned to record type group 3.


Each record type group can be assigned to one or more
parameters in the standard value key for the work center
(for example machine time). (See Customizing in Production
® Basic data ®Work center ® General data ® Standard value ®
Define standard value key). The link between time event and
parameter ensures that the calculated duration counts as an
activity (for example, when calculating the actual costs of
the operation.


The processing of an operation requires both machine time
and labor time. The time event confirmation for the
processing section of the operation can take effect on
activity u2018machine timeu2019 and on u2018processing
timeu2019, if you enter record type group u20182u2019 for
the parameters u2018machineu2019 and u2018laboru2019 in the
standard value key.


You can only confirm quantities when you confirm processing
time events.


You can only confirm activities that cannot be assigned to
a particular record type group (Set-up, processing,
teardown) by using the time event u2018Variable
activityu2019. The confirmed value is assigned to
corresponding value in the standard value key parameters.

Is This Answer Correct ?    1 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Difference between Manual reorder point and Automatic reorder point.

2505


You want to integrate pp with fico. What steps would you take?

947


What is the purpose of Catalog? how you reverse UD?

2190


What is a ‘routing’ in pp?

1063


Define gaps.

1000


List out the basic procedure for dispatching operations in capacity leveling?

1024


Standard mrp steps

1821


What happens to plan after it has been converted into production order?

1026


List out the activities carried out in production planning?

971


Explain about rough cut planning

1771


Mention what is the difference between stock transport order and stock transfer order?

1056


What is Auto GR?

1618


Can mrp be carried out for one particular level of a bom ( level code : 0001/0002 etc)?

919


What is mrp list and what is the use of it?

1076


What is the recruitment cycle?

1018