What is the difference between time ticket and time event
confirmation and when they are used ?

Answer Posted / krish

In my understanding CO11N, is generally used to confirm the
production execution at operation level or sub operation
level or


normally for milestone operation confirmation.Automatic
Goos movement can also be performed when this T Code is
executed.


There is no track of exact setup start time,end
time,execution start time and end time.


Using CO19,we can track the or post the exact or actual
setup start time,setup end time,processing start time,end
time for each


operation.


More related to Time Eevnt confirmation,


Time Event Confirmations


Every confirmed time event is assigned internally to a
record type group:


Setup times are assigned to record type group 1.


Processing times are assigned to record type group 2.


Teardown times are assigned to record type group 3.


Each record type group can be assigned to one or more
parameters in the standard value key for the work center
(for example machine time). (See Customizing in Production
® Basic data ®Work center ® General data ® Standard value ®
Define standard value key). The link between time event and
parameter ensures that the calculated duration counts as an
activity (for example, when calculating the actual costs of
the operation.


The processing of an operation requires both machine time
and labor time. The time event confirmation for the
processing section of the operation can take effect on
activity u2018machine timeu2019 and on u2018processing
timeu2019, if you enter record type group u20182u2019 for
the parameters u2018machineu2019 and u2018laboru2019 in the
standard value key.


You can only confirm quantities when you confirm processing
time events.


You can only confirm activities that cannot be assigned to
a particular record type group (Set-up, processing,
teardown) by using the time event u2018Variable
activityu2019. The confirmed value is assigned to
corresponding value in the standard value key parameters.

Is This Answer Correct ?    1 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are all the steps involved in Variant Configuration?

1383


define variable cost

822


How is time management and payroll is integrated?

747


• How are basic order dates determined?

1925


We defined sop in months. However, during sop transfer to demand management, our independent requirements are appearing in weeks. How can we correct this from weeks into months?

777






any one can provide me some sample resume for SAP PP with 0 to 1 year experience?

3703


Differentiate ‘variant bom’ from ‘multiple bom’?

825


Mention how mrp (material requirement planning) types are classified?

838


What is meant by payscale structure? How did you configure payscale structure?

742


What is process keys

1611


What is a ‘bom’?

773


Mention what is the t-code for changing production order and to display production order?

777


What is mrp group and what is the use of it?

765


What is the need of mrp list if the stock requirement list is already given?

734


Explain the gaps and the steps involved in them.

732