How to calculate cement qty of M10, m20, m25 ?
I got the formula but I lost it.
Answer Posted / jayaraaj.arumugam
Dear Friend,
in M10 grade ratio 1:4:8 using 40mm aggregate
*40mm agg - 1.52; 20mm agg - 1.57 volume of ingredient*
since 1+4+8 = 13
aggre - 8/13 * 1.52 = 0.935
sand - 4/13 * 1.52 =0.467
cement - 1/13 *1.52 =0.1169*1440=168.36/50 = 3.37 bags
Is This Answer Correct ? | 31 Yes | 22 No |
Post New Answer View All Answers
Define the various stages of the project planning process in construction.
how much of the strength comes from post-production curing
the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm
Define What is diversion tunnel in a dam?
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
What do you mean by tolerance factor of concrete ?
pls give me some basic informations in construction of a structure?
RR masonry rate analysis
How many feet are in 4 square yards?
how many digree of freedom in four bar chain
Any strength is a stress but any stress is not strength
For what building Built-on balconies are preferable? What are the advantages?
how water proof chemicals act in concrete to avoid leek?
cement mortor 1:5 for 30 m2 12 mm tk plastering so how to calcualte its rate
Explain the difference between shear and tensile strength.