Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

i have a bar of 20 and 16, lap length is 48*dia of bar,
what is the lap length here

Answer Posted / k.k

20mm lap length 960& 16mm lap length is 768

Is This Answer Correct ?    0 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to calculate the area in squarefeets ?How much area of sqft for this measurements?East 53.3ft West 54ft North 47.7ft South 51.1ft ?

1953


Why are the bolts that hold steel rails together in oval holes?

1162


List out some of the software program that can be useful for architect?

1118


What is thumb rule in quantity and cost estimation of a residential building in civil engineering??

3009


how to calculate testing date

1687


CAN V USE CRUSH SAND FOR CLAY BRICK MASONARY

1142


What is Critical path in Ms-Project ?

1202


what is the sequence of the activities in the typical under ground water tank including civil & MEP works.

2453


What are your goals?

2936


what is the procedure of wet seiving. n percentage of silt in different type of soil?

2619


Dear Frds, How can i calculate the Steel for RCC Slab, Please provide one Example also, so that i can understand very well. Ex: Area: 1320.0 Sft.(44' X 30') Span: 15'(Default). Column Size: 9"X15"(6 No.s 12mm Rods) Please Provide Calculation Details. Thankyou. Satish

2644


Explain what are the phases inspections are done by local authority while construction?

1204


What is rate of concrete surface rendering work per sqm

2015


what is mean by reestimation?

1822


As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.