how to calculate cement bag in RCC
Answer Posted / dhavaljit rathod
BULK DENSITY (SPECIFIC GRAVITY) OF CEMENT = 1.52
BULK DENSITY (SPECIFIC GRAVITY) OF 40mm AGG. = 1.57
BULK DENSITY (SPECIFIC GRAVITY) OF 20mm AGG. = 1.54
M 20 = 1 : 1.5 : 3
HENCE, (1+1.5+3) = 5.5 (Total MIX)
FOR CEMENT CONSUMPTION,
(1/5.5)X 1.52 x 1440 = 397.87 kg (where, 1 CUM = 1440 kg,
and 1.52=Cement Sp.Gr.)
SAY = 400 kg
BAGS = 400/50 = 8 nos.
Is This Answer Correct ? | 27 Yes | 13 No |
Post New Answer View All Answers
for 32 dia (EQR HYSD steel) bar how much deduction for 45 and 90 degree band
At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.
What is the minimum size of the particles of silt soil?
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2
On what basis we decide the formation level of the road? other then that of 50% Cutting and 50% Filling??
Explain the difference between shear and tensile strength.
why does the most of civil engg is not intersted to going for teaching field?
how to calculate cost of raw materials of a building for 1000 sqft & also consolidated cost of labour in a 1000 sqft building
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
1)Why we can use half brick in 4inch wall and 2)why not in 9+inch brick wall
manhole height is 1500 mm and width of brickwork is 230 mm dia of manhole covering is 560 mm brick masonry 1:4 horizontal length is 1500 mm and plaster 12 mm thick on both side 1:3. how to estimate the quantity of brickwork with mortar cement and sand for manhole chamber.
What is rate of concrete surface rendering work per sqm
cement, sand, aggregate,reinforcement & concrete consumption per square feet in multi storeyed building
What is meant by autocad?
The building has 12 columns of 12x9 in 3 rows of 4 each in a plot of 50'x30', The central row is strengthened with 16mm twisted rods. The roof area is 1500 sft including balconies. calculate the load factor per sft. Also indicate the number of roofs the building can withstand.