Answer Posted / madhu sudhan
LAPPING FOR COLUMN:- MID HEIGHT OF COLUMN WITH 1.3LD,NOT
MORE THAN 50% OF BARS LAPPED IN ONE STRETCH,THE VERTICAL
DISTANCE BETWEEN LAP NOT LESS THAN 0.3TIMES LAP LENGTH.
BEAMS:- MID SPAN OF COMPRESSION ZONE.
REFFER CODE IS 13920
| Is This Answer Correct ? | 18 Yes | 5 No |
Post New Answer View All Answers
please give the detail design for the soring and shuttering for 8.5m deep excavation in the sandy soil for 25x10 rectangular streaches
a butt weld is specified by
Whats be the minimum foundation depth of multistoried building as per height of building in individual footing?
how to absorb to site basic corrections? which are the important correction?
how many numbers of 4inch bricks and get consumed in 9 inch BB masonary wall in cubic feet.plz send my below e.mail adress
What is pre-stressed concrete?
In block work seawalls what is the purpose of slip joints?
minimum number of bars in a beam? minimum and maximum column size and beam size ? minimum and maximum aggregate size used in multistorey residential building for columns,beams,slabs?
What is meant by autocad?
i have boiler of 35 tone and wanted dig out foundation is there any body to help me to carry out calculation for the foundation like
how much percent are used 20mm,10mm?
Explain the different types of roofing systems?
How much qty of stone ; sand; cement in R/R stone masonry of 136 CUM
i want texture painting pwd data
What is alternate bid?