Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how many cement bag in 1m*m*m

Answer Posted / j.v.varma

Weight of Cement for 1 Cubic Metre= 1440 Kgs.
1 Bag Of Cement =50 Kgs
1 Cub = 1440/50
= 28.8 Bags

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is bylayer?

1106


Explain major difference between auto level and dumpy level?

1129


i have applied 40mm spacer in the concrete for tie beam. is it correct? kindly give me if there any code available

1875


what is hydrostatic paradox?

2197


a solid steel rod length 2m dia and 20mm vertically hangs from celling and has a collar firmly atteched to it. above the collar an annular rubber washer of 40mm th. having stifness k = 5n/mm is placed. determine maximum stress in the rod caused by mass of 5 kg falling through a height of 1.2m.

2309


What is the quantity of cement used for stone pitching work of 100sqm 225mm thick and cement mortar of 1:6? And how?

5119


B.M DIAGRAMS & S.F DIAGRAMS OF CONTINOUS BEAMS

2913


Define What is the best type of wood glue?

1086


what is pouring and explain

2297


in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?

2266


How to calculate paint drums per meter square

2500


what is the procedure of wet seiving. n percentage of silt in different type of soil?

2591


Is it possible to make a feature using an overdefined sketch?

1336


in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh

2226


what is the calculation of raw material for 0.35cum of m-15

1406