Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

you are the project manager of a project , customer is asking for a change in scope and agrees that it will be a CR. But you do not want to take the CR for whatever reason. How will you convince the customer in doing so

Answer Posted / girishrangaiah

I will have a meeting with the customer on this CR aspect
and explain him the importance of delevering the ongoing
approved commitments to him on time. Also will make him
understand the Time Constraint and non availability of
effective Resources for taking up the CR immediatly.
But would assure him that his CR will be given high
priority in the next phase after the existing commitments
are delivered.

Is This Answer Correct ?    39 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 778 B. 780 C. 861 D. 833

1280


Your project was just completed, accepted, and closed. As is customary for your organization, you conduct a post-implementation audit. The purpose of this audit includes all of the following except: A. Evaluating project goals and comparing them to project product B. Reviewing successes and failures C. Documenting the acceptance of the work results D. Documenting possible improvements for future projects

1082


Describe the risk in software engineering.

950


Explain the concept of total quality management.

1164


You are the project manager for a large construction project. The project objective is to construct a set of outbuildings to house the Olympic support team that will be arriving in your city 18 months from the project start date. Resources are not readily available as they are currently assigned to other projects. Jack, an expert crane operator, is needed for this project two months from today. Which of the following skills will you use to get Jack assigned to your project? A. Negotiation and influencing skills B. Communication and organizational skills C. Communication skills D. Problem-solving skills

1590


Which of the following brings together a set of tools and techniques used to describe, organize, and monitor the work of project activities? A. Project managers B. Guide to the PMBOK C. Project management D. Stakeholders

1464


You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.

1625


When a project is being performed under contract, the product description is provided by which of the following? A. The buyer B. The project sponsor C. The project manager D. The contractor

1017


Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published a document that establishes the scope baseline. Which of the following is true? A. This is the scope statement, which is an output of the Scope Planning process. B. This is the scope statement, which is an output of the Scope Definition process. C. This is the scope statement, which is a tool and technique of the Scope Definition process. D. This is the scope management plan, which is an output of the Scope Definition process.

1008


Your selection committee is debating between two projects. Project A has a payback period of 18 months. Project B has a cost of $125,000 with expected cash inflows of $50,000 the first year and $25,000 per quarter after that. Which project should you recommend? A. Either Project A or Project B because the payback periods are equal B. Project A because Project B's payback period is 21 months C. Project A because Project B's payback period is 24 months D. Project A because Project B's payback period is 20 months

1251


You are a project manager with several years of experience in project management. You’ve just accepted your first project in a foreign country. You've been in the country a week or two and are experiencing some disoriented feelings. This is known as: A. Collocation B. Diversity shock C. Global culturing D. Culture shock

983


How do you set goals for your team?

961


The primary function of the Closing process is to: A. Formalize lessons learned and distribute this information to project participants B. Perform audits to verify the project results against the project requirements C. Formalize project completion and disseminate this information to project participants D. Perform post-implementation audits to document project successes and failures

1094


You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers their products through mail-order catalogs. They're interested in knowing customer characteristics, the amounts of first-time orders, and similar information. As a potential bidder for this project, you worked on the RFP response and submitted the proposal. When the selection committee received the RFP responses from all the vendors bidding on this project, they used a weighted system to make a selection. Which process did this occur in? A. Source Selection B. Solicitation C. Requisition D. Contract Administration

1171


You are the project manager for Changing Tides video games. You have gathered the inputs for the Activity Duration Estimating process. You will employ which tools and techniques to produce the outputs for this process? A. Activity list, analogous estimating, quantitatively based durations, and alternatives identification B. Activity list, analogous estimating, expert judgment, and quantitatively based durations C. Expert judgment, analogous estimating, quantitatively based durations, and reserve time D. Expert judgment, alternatives identification, quantitatively based durations, and reserve time

1214