how much quantity of cement bags are required to fill the
one m3 of empty container.?
Answer Posted / mohamed
28.8 no of bags required to fill 1 m3 of empty container
| Is This Answer Correct ? | 9 Yes | 1 No |
Post New Answer View All Answers
How do we calculate the power of centrifugal pump?
in levelling operation the first site on any change point is back site the second site on any change point is fore site the line commenses with fore sight & closes with backsight the line comensses with back sight & closes with fore sigh
a) Difference between Ghol , Chimney & fly ash bricks b)Floor to floor height is 3m , rise=15cm , tread 20 cm , how to design staircase means steps landing
what are the code used for residental building?
what is the Purpose of Adding 20% of wet mortar & 1/3rd to Dry Mortar for PCC & Plastering & Rcc .is there any standard method for adding this .?
We are into industrial flooring (epoxy flooring) business. We buy material from manufacturers.We supply and laying the to companies. In our billing what tax/ taxes to be claimed from companies? Are we applicable for only WCT or any else?
I was once rejected for US visa in early August. But now I'm going again for interview next week. What are the chances that I will faced the same VO????
What is made from large rocks, which protects the base of cliffs?
how much cement sand n bricks required in im3?and how much in plaster?
In an aggregate blending plant, water is sprayed before blending is performed. If the fine content in aggregate is as high as 25 %, will not the fines form into lumps / balls and distribution will not be uniform ? Further, the fines will stick onto the interior of pug mill and its content will be low. The mixed material is stockpiled for weeks / months before use. Will it not be better that blending is done in dry condition, and water will be added only during compaction at site. Please forward your comments and suggestions.
usually hand broken stones are used for cement concrete 1:4:8 in foundation of single /two story houses with a view of economy in construction.what advantages it will give if you use machine crushed stone in place?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
How do you measure water flowing through 300mm diameter pipes?
Define Workability ?
What is the minimum size of the particles of silt soil?