Could anybody pls give ans of boiler 3 element control system?
Answer Posted / naik muhammad
Most boilers of medium to high pressure today use a “3-
element” boiler control strategy. The term “3-element
control” refers to the number of process variables (PVs)
that are measured to effect control of the boiler feedwater
control valve. These measured PVs are:
▪ liquid level in the boiler drum,
▪ flow of feedwater to the boiler drum, and
▪ flow of steam leaving the boiler drum.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What is the purpose of LO Overhead tank in turbines.
What is the Working principle of Dozing valve?
dear friends, i have seen flow as the selection critriea in presure guage (bourdon tube) and i would like to know what is the relation between flow and performance of pressure guage other parameters i found in the data sheet are pressure max. 1ksc temperature max. - 50 deg c line size - 80NB operating range - 1ksc pr. guage range - 0-2 ksc thank u,
If we increase only P what will be controller action ?
Difference between dcs and plc including date processing and architecture.
How would you choose differential range?
There are two chlorination tonners both are connected to two pressure swithes and the pressure switch is connected to SOV which operates the valve to changeover the tonner selection i.e if pressure one tonner goes low the other tonner should come in line if it is inautomatic selection design a circuit using relays ?
how can i calibrate the temperatuture gauge used by temperature bath(dry block) i mean step by step procedure?
installation process of orifice,a question asked for confusion creation in interview by BARC 1.if orifice is tightly fitted with pipe ,it will act like venturi 2.if orifice is left hanging in between liquid it will not create the pressure difference exactly,
How to Calibrate Vortex Flow transmitter in field
what effects a surging can produce in the compressor
What is the use of gauge?
Please any one can provide latest aptitude test,technical test and interview questions for tata consulting engineering (TCE) i need it asap thanks in advance
1.can you use SCADA instead of DCS,DCS instead SCADA 2.Difference between DCS and PLC,can their role be reversed i.e. role interchange 3.Difference between RTU and PLC
what is the difference between profibus and controlnet networking.