Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

what is step foundation

Answer Posted / a k vaidya

In order to distribute load on larger area ,as per the
bearing capacity of soil,width of foundation is increased
down wars in steps . This is adopted espewcially in stone
or brick masonary.

Is This Answer Correct ?    7 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the difference between shear and tensile strength?

1193


Used Cement & Sand in 1 Square Meter or 1 Square Feet For Brick Work 0.115mm ? (1:4) (1:6)

2478


is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?

5440


Define What is made from large rocks, which protects the base of cliffs?

1130


why is M30 grade Concrete use for Foothing & Column M50

3555


What is the thickness of slab for 600 sq each) 2 slab construction. What should be the size of steel rod?

1874


what is idealized curve for concrere and steel

2368


the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum

2091


how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend

2072


Define relative co-ordinates?

1185


With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr

2499


What is critical path method (c.p.m)?

1197


What is geopolymer based concrete?

2776


What are the different theories of failure under static load?

1355


Which are the top apps for you civil engineer?

1273