A bill was raised by contractor which read as follows
1.) Excavation in normal soil upto 1.5m - 250 cum
2.) Excavation in normal soil 1.5m to 3m - 240 cum
3.) Excavation in soft rock - 350 cum
4.) Excavation in hard rock - 250 cum
5.) Filling with available soil - 825 cum
6.) Filling with bought out soil - 1100 cum
How can I verify the above quantities, especially for item
no. 5 & 6?
What checks are necessary before releasing the bill ?
Answer Posted / gkreddy
contractor should be ansure there must
and should maitain JMR( Joint
Measurement Record) for produce the bill
otherwise bill should be rejected.claint
also insist the contractor to maitain JMR.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
can we find any technical issue if we are gong to change the dimensions of steel beams from one type to another type IE if there are any equievelant data base to find solution for problem of changeing sectios of beam from one type to another with the same cross sectional area.
What is the use of extend command?
Volume of 25kg putty bag & 40 kg putty bag volume??
What are the advantages of building a dam on the river nile?
What sizes of stones chips are used for foundation, column and floor casting. Please answer in detail.
What is the density of most of construction materials?
What is the average density of soil?
WHAT WII BE THE WATER ABSORPTION POWER OF WOOD ?
WAP to print 1) 1 1 1 1 1 1 1 1 1 1 2) 1 2 3 4 5 6 7 8 9 10
What is bmc stands for in bmc software?
1m square 20mm plastering how much of water need curing work
Why was the empire state building made of steel?
how to clculate the %of concrete strenght achive after curing?load
Is there any course for billing available in Mumbai? If yes then please mail me the details..
Please tell me the quantity of cement, sand, flyash, foaming agent required for 1 cubic meter of cellular lightweight concrete blocks. also , is there any admixtures required for the CLC blocks production.