A bill was raised by contractor which read as follows
1.) Excavation in normal soil upto 1.5m - 250 cum
2.) Excavation in normal soil 1.5m to 3m - 240 cum
3.) Excavation in soft rock - 350 cum
4.) Excavation in hard rock - 250 cum
5.) Filling with available soil - 825 cum
6.) Filling with bought out soil - 1100 cum
How can I verify the above quantities, especially for item
no. 5 & 6?
What checks are necessary before releasing the bill ?
Answer Posted / gkreddy
contractor should be ansure there must
and should maitain JMR( Joint
Measurement Record) for produce the bill
otherwise bill should be rejected.claint
also insist the contractor to maitain JMR.
| Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
What are the joints wants to made in masonry where door opening, arches like etc..
What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?
Which is the direction of negative angle?
Why Vitrified tile are getting pop up.
TELL ME THE EQUATION FOR OGEE SPILLWAY
Why you are leaving present job?
what is constat for brickwork
how to calculate the mortar for 10'*10' size room for both plastering and for masonry work?
How is improve my knowledge in construction industries....
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
How to find CN by using arcgis 9.3?
What is reinforced concrete?
What is an ortho mode?
What is the use of extruded feature in solidsworks?
a butt weld is specified by