In two way slab where should we stop the work at end of the day?
Answer Posted / ajay kulkarni
it should be a little ahead towerds center form point of
contraflexure to allow for bonding roughfly @ L/3 from
either ends for two way slab.
| Is This Answer Correct ? | 11 Yes | 0 No |
Post New Answer View All Answers
Explain what is the difference between built area and super built up area?
HOw much % of premium on DSR-2013 currently
what is a well
HDPE pipe standard bends using for TSE irrigation? is it possible to use 30 degree?
Is there any course for billing available in Mumbai? If yes then please mail me the details..
The concrete slump recommended for beams and slabs; is?
the volume of cement req for 70cum of brickwork in 1:6 cement mortar is approx is equal to 3cum 5cum 7cum 1ocum
CAN WORK WELL UNDER DEAD LINES OR PRESSURE?
Doul Bar reinforcement and details of drawing.
How did street originate in the plumbing term street ell?
significance of specific surface area of particles?
What is high adherence steel bar? I have a general specification which refers to High Adherence steel bars, coils and meshes to BS EN 10080 and BS 4449 or BS 4483. Is this just general re-bar or is there something different about it? The spec originated in France.
what is the weight of 12mm aggregates?
How will be cutting in timber plate size 600*400 column size
What is the average density of soil?