How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step

Answer Posted / zuber ahmed

Volume of Dry Mortar = 35% of volume of Brickwork

Volume of Mortar required = 0.35 + 1 = 1.35 cu.m.

Cement required = 1/6 X 1.35 = 0.225 cu.m. =6.8Bags

Sand required = 5/6 X 1.35 = 1.125 cu.m.

Bricks required = 500 Nos.

Is This Answer Correct ?    10 Yes 43 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

all technical question

1696


what is the productivity in aluminium shuttering per day

1587


What is semirigid connections?

1643


how to disign cuplock shuttering and it's matireal requirement snd any related web site

2529


how to caluclate sienerge qty in construction in ap

1951






what is the cost of rcc roof casting of 400 sq. ft. in kolkata

3246


1.what is the mix proportion for cement soil compressed earth blocks? 2.how to calculate the mix proportion for cement stablised earth soil blocks?

1790


What are the different methods for drawing an arc?

712


What is the biggest dam in america?

675


The concrete slump recommended for beams and slabs; is?

771


material used for mendrel use to bend epoxy coated rebar

1712


Which condition will prevail for the design of a swimming pool ? When the pool is empty or when it is filled ?

1981


how beam.coloum ,slab, footing are designed as per indian code.. detail procedure?

2139


What does a construction cost covers and what does not?

743


How many pyramid in egypt?

645