How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / zuber ahmed
Volume of Dry Mortar = 35% of volume of Brickwork
Volume of Mortar required = 0.35 + 1 = 1.35 cu.m.
Cement required = 1/6 X 1.35 = 0.225 cu.m. =6.8Bags
Sand required = 5/6 X 1.35 = 1.125 cu.m.
Bricks required = 500 Nos.
Is This Answer Correct ? | 10 Yes | 43 No |
Post New Answer View All Answers
all technical question
what is the productivity in aluminium shuttering per day
What is semirigid connections?
how to disign cuplock shuttering and it's matireal requirement snd any related web site
how to caluclate sienerge qty in construction in ap
what is the cost of rcc roof casting of 400 sq. ft. in kolkata
1.what is the mix proportion for cement soil compressed earth blocks? 2.how to calculate the mix proportion for cement stablised earth soil blocks?
What are the different methods for drawing an arc?
What is the biggest dam in america?
The concrete slump recommended for beams and slabs; is?
material used for mendrel use to bend epoxy coated rebar
Which condition will prevail for the design of a swimming pool ? When the pool is empty or when it is filled ?
how beam.coloum ,slab, footing are designed as per indian code.. detail procedure?
What does a construction cost covers and what does not?
How many pyramid in egypt?