Big Bang Model isn't preferable for higher cost project?
a. True
b. False
(Need the answer urgently)
Thanks!
Answer Posted / mfsi_priyankaa
True..because in Big Bang integration testing we wait until
all the modules have completed then at the end we do
integration testing at once.So,if any bug found at that time
then it will cost much to fix that because if there is any
bug in a single module then it may affect to other modules.
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
How does compatibility testing differ while testing in Internet explorer and testing in Firefox?
Can you explain usability testing?
How soon the bug should get fixed?
Diffrence b/w functional testing,functionality testing,system testing?
What criteria would you use to select Web transactions for load testing?
what is date field test case
What is the difference between code walkthrough and code review? What is the difference between walkthrough and inspection?
what are the tests u did in entire project? when it did in the project? (means at the release build to end of project) plz explain clearly
What are tools of performance testing?
what are the risks and contingencies u had in ur project?
If anyone have attended interview with deloitte for the post of senior manual test engineer. Please share the interview process and the questions asked. How to prepare for the interview. Thanks in advance
How would you test a service oriented architecture (soa) web application?
what is functional testing terminologies
Being an Manual tester, what will be the role or activity in test plan ?
whar are the contents in db testing test case template