Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

What is the cost of Brickwall ( 4")(1:4) thick wall total
Area 245 sqft with plaster(1:6). With all materials
including.

Answer Posted / prashanth

For birck wall-14000/-
For Plastering one side -5000/-

for 245 Sqft

Is This Answer Correct ?    1 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

i have to give lap joint fo 1Mtr steel of dia12mm,whenever i did mistake i cut less 5cm plz tell me how much i will give lap joint so that length comes 1Mtr

2083


material used for mendrel use to bend epoxy coated rebar

2219


There are two buildings one taller and one shorter whose time period will be grater and similarly the frequency ?

1713


how to calculate valuation for the old building?

2477


Pls help me to arrive the rates for centering shuttering for highbay using H-frames?

2412


what is the amount of absorption of slurry in shuttering ply board. what is the amount of slurry leakage allowed for 1 m3 of concrete.

2375


how to identify the failure of building by expansive soils

1694


brickwork labour rate per cum ?

1669


how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.

3835


57. Calculate the volume of a truck loaded with stone chips whose data are as follows– 5 Top Length - 13-9, 13-10, 13-09 Bottom Length - 13-11, 13-10.5, 13-10 Top width - 8-7.5, 8-8, 8-7 Bottom width - 8-7, 8-8, 8-7.5 Depth - 2-0, 1-11.5, 1-10, 1-11, 1 -10.5, 1-11.75, 1-11

9577


I want to know the material required per Square foot in rcc roof i.e.Steel ,Cement,

2034


WHAT IS YOUR CURRENT SALARY

2355


How much is the cover for slab?

1339


VAT and CST ? Which benefits for buyer ? Why benefits?

1871


What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil

2810