If the cost of work is 20000 and retantion is 5%, tds is 1%
and wct is 2%. what is d total amount have to pay?
Answer Posted / jitender
Cost of Work - 20000.00
Add:-2% WCT 400.00
________
20400.00
(Security-Retention Money) 1000.00(Less)
________
19400.00
Less TDS 204.00
________
Amt Paybel 19196.00
Is This Answer Correct ? | 3 Yes | 3 No |
Post New Answer View All Answers
While posting of FB50 entry therE showing errro msg " NOT ASSIGN COMPANY CODE OR CALCULATION PROCEDURE"
Whether setting up of diary plants comes under CMA under Farm Sector or Non Farm Sector
Q13. Journalise the following transactions: Proprietor withdrew for private use Rs.4000/- from bank and 6000/- cash. Goods Costing Rs.5000 was burnt by fire. Purchase Machinery for cash Rs.150000/- and paid Rs.2000/- on its Installation. Charge 5% Depreciation on building costing Rs.200000/- and 8% Depreciation on Furniture costing Rs.5000/-. Prepaid Salary Rs2000/- Kapil who owed us Rs20000/- become insolvent and nothing is received from his estate.
about tally erp9
What are the stages involved while preparing business blue print with examples?
Entrance Exam question & Answer required
Please do tell me about the questions which are asked at BACS FINAL ROUND.
Clasify capital
distinguish between price rate and time rate?
Hi Iam Arun D. I m short listed for Karnatka bank interview. Can anybody share ur experiences regarding Bank interview of karnatka bank which was held on dec for Officer's post. Please help me I f u can. thanx in advance
i did mba finance in 2010,but i came from life sciences to mba,i know in interview they ask y u came from sciences,so what i tell?pls reply me.
why do you want to work here?
what is CDD’s configuration
let me know the minimum Accounting Heads in an accounting system
what is Derivative Documentation,Derivative Settlements,Derivative confirmation?