A bill was raised by contractor which read as follows
1.) Excavation in normal soil upto 1.5m - 250 cum
2.) Excavation in normal soil 1.5m to 3m - 240 cum
3.) Excavation in soft rock - 350 cum
4.) Excavation in hard rock - 250 cum
5.) Filling with available soil - 825 cum
6.) Filling with bought out soil - 1100 cum
How can I verify the above quantities, especially for item
no. 5 & 6?
What checks are necessary before releasing the bill ?
Answer Posted / u.arunkarthick
here the total excavation qty is 1090 m3, then minus the qty
of concrete used for footing and add consolidation of soil
as 2 to 3%, example if we excavate 1m*1m*1m = 1m3 of
excavated earth is there, then refill that area needs 1.2m3
because of soil consolidation.
Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
What is the tensile strength of marble?
At one time what is the height of Lift for concreting for Bridge Piers Class B Loading and refer the code.
Define block?
what is the specific gravity of rubble in plum concert
hai, kindly send anyone for output workers format details for construction project in foundation to finishing.
What happens to Load at yielding ?
3. A vane 12.5 cm long, 8.8 cm dia was pressed into a soft clay at the bottom of borehole. Torque was applied and the value at failure was 55 N-m. find the shear strength of the clay on a horizontal plane.
psc girder detail
Give me an example of a time when something you tried to accomplish and failed.
What are the RISKS during the project construction?
what is the difference between natural draught cooling tower and induced draught cooling tower
I have completed building maintenance course in mcvc stream .. can I apply for the post of " sthapstya abhiyantriki sahayyak"?
How to calculate Cement in bags ,sand in sqft and aggregate in sqft for 1cum M25 grade concrete
How to find out slope footing concrete
What should be the standard roof height like to be?