Answer Posted / sandy
First class brick 75 kg/cm sq.
Second class brick 50 kg/cm sq.
Third class brick 35 kg/cm sq.
| Is This Answer Correct ? | 3 Yes | 2 No |
Post New Answer View All Answers
how do i remedy a foundatiom that the column bases was cast and aftet 28days crushing the conprehensive strength of the concrete fall below the specification 25N/mm2
A super elevation of 60 cm has been provided on a 8m wide road and a curve of 260m radius .calculate the max.speed in km/hr of the vehicle that can be negotiated safely? Plz answer with full solution.thanx
What is Rankine Cycle?
Why nautical mile is different from statute mile?
at which depth the construction of tunnel is economical from cost and engineering aspect.
What is the difference between routing maintenance and major maintenance in school facilities?
How to determine dia of steel for use in column,slab etc. i mean how to calculate the diameter of steel which is to be used in structures.
What is the use of mirror command?
Define What is the difference between routing maintenance and major maintenance in school facilities?
how to take concrete quantity for precast segment for viaduct project?
Define What is aggregate?
How to arrive d*d/162 , for finding the kg per meter , wt of steel
TELL US ABOUT A TIME WHEN YOU FAILED TO MEET A DEAD LINE. WHAT WERE THE REPERCUSSIONS?
What are wooden shingles?
What are the responsibilities of a site manager?