Answer Posted / guest
RCC steel required for slab
= 0.5 to 1.0 % ( 40 to 80 kg/m^3
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What is meant by cad?
What is the difference between Hinged and pinned in Column ends
how to calculate detail quantity of bricks and mortar for 500 cu.ft masonry work. consider wall thickness 9 inches
Calculation of curtain wall of box culvert
1.what is the mix proportion for cement soil compressed earth blocks? 2.how to calculate the mix proportion for cement stablised earth soil blocks?
about higyway engineering
why +1 to be followed for calculating the no of bars in BBS. Please explain
five benefits of using standard terminology in the measurement process
What are the benefits of rcc pipes over steel designed pipes?
PL.tell me about civil engineering questions with answer
The largest size of paper used in plotter to print the drawing made by Autocad .
Draw the cross section of a boundary wall and label its part with detailing?
How to test cement,sand,20mmbluemetal,40mmbluemetal,bricks,concrete by visual and instrument
Method of findingthe dry ingredient quantity of 1 m3 concrete. what is the difference between static and dynamic induced emf? Testing charges bill given for Rs. 32,000/- but not added service tax in this bill. So, How much TDS will be deduct
Steel requirement in kg of 6" thk slab Total qty 32.64 m3 Beam / column qty 35.39 m3