Answer Posted / satya paul
function of dry lean concrete is to provide firm base to support traffic over pqc pavement.there should be no bond between pqc and dry lean concrete.after laying dry lean concrete with the help of paver and compacted with roller passes.minimum eight times up and down i.e total 16 passes.it should be sprayed with MC0 grade bitumen primer.cracks will appear from 10m to 15 distance depending upon cement quantity,mix grading of aggregate ,temperature and wind speed,
before laying pqc ,500 micron anti static polythene sheet shall be laid over dry lean concrete.cube strength of dry lean concrete shall be 5n/mm2 and above.higher cement depends upon the strength required for sub base.max size of aggregate shall not be more than 20 mm.good mix falls in the middle portion,weaker mix falls at the ends.take sample from the end and compare with the middle portion of concrete.difference in strength shall not vary more than 6%.
Is This Answer Correct ? | 20 Yes | 3 No |
Post New Answer View All Answers
How to find the cuplock pipe qty in staging for Minor bridge?
how to find ssm in foundation?
Why are separation membranes used between concrete pavement slab and sub-base?
VAT and CST ? Which benefits for buyer ? Why benefits?
Are you ready to relocate with your immediate family to United States as a new employee?
What do you mean by the word 'shear'?
What is the nature of duties & responsibilites senior civil engineer ?what is self confident & satisfaction should be a senior civil engineer?
How to calculate concret slab? W l t(4mts*5*2fts) ratio m25 grade pls tell me procedure
What is the tensile strength of marble?
In reclamation works what are the importance of geotextiles and sand?
may i know the detailed description of cutting length
how can we calculate steel value, depending on load
What are the advantages of cad software’s?
can u plz send me ntpc placement papers(civil engineering) at mohit_verma21@yahoo.com
what is the weight of 12mm aggregates?