GIVE THE TEMPERATURE RANGE OF PLATIUM RESISTANCE THERMOMETER.
Answer Posted / george mathews
PT 100 RTD can sense the temperature and can work good in a
temperature range between 0 degree c to 300 degree c.
| Is This Answer Correct ? | 1 Yes | 1 No |
Post New Answer View All Answers
WHY THE DEGREE OF VALVE PLUG AND VALVE SEAT IS SLIGTLY DIFFERENT I CONTROL VALVE TRIM DESIGN
Why all the drains(Gland sealing,ESV,Casing inlet etc) are directly connected to the flash tank instead of hotwell of the condensor in the power plant? My Email Id:naba02222@gmail.com
why direct mounted pressure transmitters is always installed with DBB ( double bleed block) valve in process line or top of the tanks ?
on interface level transmitter model(RTG3302-EMERSON) What is threshold valve how can we select correct threshold value T1,T2,T3,T4 When interface water & hydro carbon
Punj lloyd is coming in our Jadavpur Universtiy campus for campus placement. Please send me some hints about the writtend exam. My email id is subratafriends@gmail.com
If a control valve is hunting means means if we are giving 50% to the cv, the cv will open at 51% then slowly slwoly it will reaches 49% , so what to do for solve this problem. The cv is double acting and mounted for anti surge operation, it having 4 nos. volume booster, one sov, one positioner, etc..?
hiii.... can any one provide me previous years question paper of hindustan petroleum for instrumentation engineering???
Calibration procedure for electro magnetic flow meter
if my flow is 20000 m3/h than which range of DPT i have to use????
What is the purpose of LO Overhead tank in turbines.
A PLC is programmed to drive three motors A, B and C as follows : After running motor A for an hour, motor B should get ON and motor A should get OFF. And after running motor B for an hour, motor C should get ON and motor B should get OFF. And after running motor C for an hour, motor A should get ON and motor C should get OFF. (That is, a cyclic repetition with time period one hour) Now, the second condition is: If any motor gone faulty and is tripped, the consecutive motor should get ON and the faulty (tripped) motor should be eliminated from cyclic repetition. The remaining two motors should bear the cyclic repetition of one hour each. (For healthy motor take logic as high and for tripped motor take logic as low) Now, the third condition is: When motor A load(Amps) exceeds 60% of its rated load, motor B should get ON in parallel to motor A. And when both motors A & B are running in parallel, and if their load exceeds 60% of their rated load, motor C should also start in parallel to A & B. [Here the cyclic repetition is eliminated, until their loads become normal(40%)] [Take logic high(1) for load at 60% and logic low(0) for load at 40%] Now draw a flow chart or a ladder diagram to fulfill the above condition.
What care will you take in the installation of control valves,SCADA,DCS and FOC in Oil and Gas Project?
you are on site,the plant trips,you are approached by operations,what do you do?
i am preparing for BARC ,so plz mail me how to prepare for BARC. ALSO IF POSIBLE SOME RELATED QUESTIONS. MY MAIL ID IS khushi_4uall2003@yahoo.co.in
what is function of sensor, and how is it work , explain with difination