We are getting supply at33kvand it stepdown to 11kv.So Our
requirement is 11kv voltage.why we draw 33kv from the grid
instead of 11kv?
Answer Posted / naresh kumar
Reasons:
1)to reduce the conductor size of the feeder.... i.e, by
increasing the voltage levels the current level decreases to
maintain constant power.. the feeder design depends on the
current levels so lesser currents lesser will be the cross
section...
2)by increasing the voltage levels the current levels
decreases so the i^2 R losses decreases and the transmission
efficiency increases.
| Is This Answer Correct ? | 17 Yes | 0 No |
Post New Answer View All Answers
what are the differences between 'exhaust fan', 'heavy-duty exhaust fan' & 'super heavy duty exhaust fan'. what are their power ratings ?
HOW DOES THE ELECTRONIC ENERGY METER WORKS?
would you please give me any idea about the BARC interview question on electrical? i have an interview on 1st july.....plz hlp me.......its urgent......
plz send me Bhel, Mahagenco, sbi previous exam paper for electrical engineer on my email-id kambali_smita@yahoo.co.in
I want to make street light with solar system ... What may I do for procedure and how much of estimation for each material ... If any one knows guide me and inform this id : aravindd7@gmail.com
which type of effect of turbine and generator reverse power protection ?
In vapour absorption refrigeration machine fluids used are
what is size of 3phase 4wire cable to be used for 11 ton ductable A.C and how to calculate cable size for different load
why u r living from presentaly working.
pls tell us AC plant are how do work and parts name with picture
What current flows in the transformer primary when its secondary is open?
My load is 1635 KW. & current pf is 0.884, I have to improve it for 0.99.Please suggest what KVAR value is needed?
what is the physical connection of a analog i/p to a analog i/p module (ab plc)and through a analog o/p module(ab plc) to a analog o/p . and how all the process control by scada
Difference between HRG and NGR. Are they both the same thing
detailed procedure how we calculate cost for pcc m10 and rcc m20 including centering and labour excluding steel/ iron