how to calculate steel columns beams and slab please give
me brief calculation
Answer Posted / surajit naha
plz follow the types of problems and design of mixing with
quantity survey.
enerally we assume 1 to 5 percentage steel in columns of
concrete.1 to 2 percent in beams,0.7 to 1% in slabs and .5
to .8% in footings.
if concrete is 100 cum.
than in column if we take 1.5% steel it will be 1.5 cum steel.
1.5x7850kg/cm3(density of steel.)
quantity of steel determined.
| Is This Answer Correct ? | 24 Yes | 18 No |
Post New Answer View All Answers
Scaffolding IS code NO.
Name the main components of a cad gui?
Explain what is change order request?
How much time Required for PPR pipe network testing
rate analysis for cement pointing 1:4 , for 100 sq m
how do you stabilize a waterlogged area in road construction
How is calculate the cube molt
Suggest how many column, beem, etc required for 30 mtrs x 21 mtrs width x 8mtrs height for industrial shed of ground floor. I want to know the quantity of tmt steel consumption and Concrete consumption for budgeting
What is M40 _ TOR - EQ and B.F.S
How do you change a dimension value in solidsworks?
Tell me about triple point of water.
Explain the water bound macadam roag
what happening if we casting HV shunt reactor foundation pad at 50cm height different time (One day difference)
we want build 10ft height ,tostore 4 litresof water.what is theground basement for steel andcement andsand.please send us basment calculation?
what are the challenges of being a team leader and a supervisor?