the amount which paid to contractor before starting work.
what does it calls?
Answer Posted / dheeraj singh
Mobilization advance which will be deducted in running bill
as per norms of Contract, as per prorata basis (complete
recover upto of work completion 80%), we will deduct %of
Givin/80 for example, M.A.-10%, than recoverable
amount=10/80=12.50%
| Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
what is Brest Wall?
what are RIB slabs explain about it
about higyway engineering
What is an ortho mode?
in a corner footing of a building, column lies in one corner. in this condition i want to know if the reactive pressure of soil will be uniformly distributed throughout the footing or will be uniformly varying as in the case of eccentrical loading.
in a building why we are using T beams? why can i adopt beam bottom & Top level as same as slab bottom & Top level?
What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?
explain the advantages of total stasion
how to Concrete cubes testing curing time 7 days casting date 24.05.17 testing date ?
What is the release of lien?
What is zoning permit?
How are freeway bridges built?
what could be the production cost of 1 cum of concrete by CP30 plant
Rate analysis of 150mm, 100mm, & 230mm thk BBM work
What is the average density of soil?