what is the pre commissioning test to be carried out on LT power panel at site?
Answer Posted / arasusulo
checking the all of bus
bars tightness and visual
short at phase to phase and
neautral...
then megger the separate
phase and ntral bus too.
then circiut braker
condition tooo.then charge
the supply and check ph
voltage and line voltage.
switch on the braker then
dstrbt the suppply by the
feeder what it is..?
| Is This Answer Correct ? | 19 Yes | 1 No |
Post New Answer View All Answers
how to calculate units consumption for a 12 hp motor /hr.
what is the difference between electrical and electronic choke?
what is the advantages of having in-built acvvvf (without seperate inverter in the control panel)in the drive system of elevators?
what is the requirement regarding earthing of Single conductor with AWA
How we calculat the NGR of 3phase Generator, Our generation voltage 11KV
How to test the vector group of a Yd11 transformer? what are the relations to be checked between various vectors to confirm this vector group?
Why MCCB is Getting tripped sometimes when there is no load in the Midnight ?
what is the breaking capacity and making capacity of circuit breaker and how
how to select diiferent power transformers of same capacity on no load loss and full load loss by economical point of view.?
how to determine Sq.mm size of finolex power cables.
what are symmetrical and non symmetrical components in electrical installation.
How does the phase sequence controller works, how it identifies the phases? confirm working principle
Explain the operation principle, advantages and disadvantages of the following converters: a) A 12 pulse converter b) A Switch-mode inverter c) A thyristor inverter
how to produsing geretor power
How a capacitor discharge weld power supply works? what is the use of a pulse transformer?