How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / mohammed aijaz hussain
Volume of Dry Mortar = 35% of volume of Brickwork
Volume of Mortar required = 0.35 X 1 = 0.35 cu.m.
Cement required = 1/6 X 0.35 = 0.058 cu.m. = 1.67 Bags
Sand required = 5/6 X 0.35 = 0.292 cu.m.
Bricks required = 500 Nos.
| Is This Answer Correct ? | 64 Yes | 45 No |
Post New Answer View All Answers
in 2 way slab can additional compressive reinforcement can be provided if yes than in which conditions it is required ?
GIVE US DETAIL OF YOUR PRESENT EMPLOYMENT STATUS?
what is density of 20mm coarse aggregate.plz send answer my below adress e.mail
what is civil engineer greatest strength and weakness?
Consumption of Binding wire for fixing of cover block in vertical surface
During reclamation how can the occurrence of mud waves can be rectified?
Will going from a 3-tap to 6-tap increase water pressure?
in 100 cft = 1350 bricks in 100 cft = ? bloks
I Want To Know Quantity of Cement Conc. & Sand in Column of 9"x9"x10'
Why the statue of liberty is made of copper?
Can inverted beams used in pipes during construction?
what is the breaking strength of wall tiles
please send me bhel questions on rupesh.017@rediffmail.com
How to do base isolation using ETABS software?
can we find any technical issue if we are gong to change the dimensions of steel beams from one type to another type IE if there are any equievelant data base to find solution for problem of changeing sectios of beam from one type to another with the same cross sectional area.