How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
Answer Posted / mohammed aijaz hussain
Volume of Dry Mortar = 35% of volume of Brickwork
Volume of Mortar required = 0.35 X 1 = 0.35 cu.m.
Cement required = 1/6 X 0.35 = 0.058 cu.m. = 1.67 Bags
Sand required = 5/6 X 0.35 = 0.292 cu.m.
Bricks required = 500 Nos.
| Is This Answer Correct ? | 64 Yes | 45 No |
Post New Answer View All Answers
How much cum. Brick work can do by 1 madon
why & what is perchatage we are using fly ash in concrete?
Why are steel plates inserted inside bearings in elastomeric bearings?
What is the best type of wood glue?
Can we use the flyash bricks in brick bat coba?
can i get hindi version of is codes based on civil engineering?
What is the difference between pvc,cpvc and upvc and where it is used as per their properties?????
how to remove the quantity of metal 1 and metal 2 in concrete
How much quantity of cement and sand required for the inlining of 610mm dia MS pipe 8.7mm thk.Inlining thickness is 10mm and CM ratio is 1:1.5.
Is it possible to make a feature using an overdefined sketch?
What is an ice dam sock?
though u r a civil engineer, y r u interested in tcs???
can stub column take the load as main column
What are the reasons for geotechnical site investigations in uganda?
about higyway engineering