What is the difference between "working stress method"
And "limit state method"?
Answer Posted / anjali
• In working stress,Stresses in an element is
obtained from the working loads and compared with
permissible stresses.The method follows linear stress-
strain behavior of both the materials.Material capabilities
are under estimated to large extent.moreover Ultimate load
carrying capacity cannot be predicted accurately.
• Whereas in limit state method, stresses are
obtained from design loads and compared with design
strength.In this method, it follows linear strain
relationship but not linear stress relationship (one of the
major difference between the two methods of design).The
ultimate stresses of materials itself are used as allowable
stresses.The material capabilities are not under estimated
as much as they are in working stress method. Partial
safety factors are used in limit state method.
| Is This Answer Correct ? | 69 Yes | 4 No |
Post New Answer View All Answers
How to convert 20 dia bar to 16 dia bar in beam without reducing the steel weight
What should be the maximum allowable time for placing ready mix concrete? The specification requires concrete placement within 90 minutes of batching at the plant. What is the significance of this 90 minutes & should this be used as a rejection criterion? What effects does the concrete has after that time period?
In case if concrete box girder bridges how is the number of cells determined?
how many re use can use shutting material. timber ? ply? steel? plastic? fibre? aluminium? Doka?
What is the density of 1:1.5 (Cement:sand) ratio in plaster? And Conversion in 12.5 mm thickness per square meter? Howmany Kg of Cement square meter in ratio of 1:1.5?
A sieve analysis results in 100% retained in no. 50 Sieve, the fm is?
How many feet are in 4 square yards?
Why is concrete cube test carried out?
residential buildings,mixing of concrete,structural,construction material,site handling.
Suppose you planning to paint newly fabricated workshop building made of structural steel of 10 tons total mass. How many litters paint primer for 1 coat and 2 coat of top coat?
Which type of plywood & sizes using in construction projects ?
What is the method of soil replacement test?
Why do we not deduct steel volume to find actual volume of concrete in practical as we have studied that,,, actual volume of concrete = volume of column- volume of steel pls explain with reference of IS code?????
what is the use if we fixed butterfly ties in column and masonry work joint?....where we have to fix(distance)..
Why are separation membranes used between concrete pavement slab and sub-base?