what"s the formula to find the cement,sand,aggreegate(45mm)
requirement for PCC?
Answer Posted / ajith
1 Cement 4 Sand and 8 Coarse aggregate
One M3 of PCC hence requires 0.076923 M3 of Cement
0ne M3 Cement =1440 Kg
0.076923 X 1440 = 110.7692
Or 2.22 Bag of Cement
| Is This Answer Correct ? | 17 Yes | 9 No |
Post New Answer View All Answers
What is c.g.i sheet which used for roof??
sir tell me the formula for calculating the volume of 380mm dia double under reamed pile of 4.0 mts depth.
What is the software used in civil engineering?
What is the difference between undo & redo?
what r the precaution for high in atp tempareture,low in atp tempareture
How to calculate concret slab? W l t(4mts*5*2fts) ratio m25 grade pls tell me procedure
Would you cause a 55-gallon drum of water to weigh more by climbing in?
How to calculate brick work quantity?? Block work quantity??
How many cement sand ballast in cc 1:4:8 40mm
step by step procedure to find out the percentage of steel in coloum,beam,slab,footing in detailed
Explain the different types of building contracts?
hai, kindly send anyone for output workers format details for construction project in foundation to finishing.
I what know about life time of frp tank plz explain about it specifications & other details
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
in staad pro. modelling for a parallel scissors chord truss, when i assigned roller support i.e fixwd but with all Fx, FZ, Mx, My and Mz release except Fy... the analysis results " in stability at a joint, with direction Mx or My..what could be the reason...anyone please explaing