How to conduct the Hydro & Pnumatic test as per DIN & ASME
sTANDERS?

Answer Posted / ankur sahu

first create a loop in which pressure all over is constant .
then make all vent open to remove all air inside the loop
and blind the end of the loop with required thickness. then
filled water and maintain pressure 1.5 times of the design
pressure.

Is This Answer Correct ?    4 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Will a steel cable become longer if it is heated while under load? Explain

660


What is the b check value of a 4bt engine

1137


i am studying in bechanical engineering in M,S,University at Baroda.i and my friends want to take one month industrial trainning in mechanical engineering company.pleas send some company's name and procedure.

1477


will I find the mechanical engineering interview question for asian paints?

1056


can someone explain tolerances on bolts what the symbols mean

1579






How much is 1 kn in kg?

684


What are the causes of damage to propellers?

1537


What is the difference between "stress and strain”?

630


What ill be the shaft diameter with clearance having a bearing bore is 30mm?

2761


where is the steam trap connected in boiler distribution?

1525


what is electronically operated pneumatic valves? give one example

1632


How to operate soot blower boiler and economizer?

1708


I need BHEL Engineer Trainee written test papers in Mechanical stream.

1841


What is the effect of friction on flow of steam through a nozzle ?

687


composition of cast iron fc-500,fc-550,& fc-260 which is use in sheet metal industries as a piller set

2996