What height of a 3.5 m high 300 x300 mm proposed col. can
be casted at a time ?
Answer Posted / ajeet kumar bhatnagar
As per the I.S.code concrete should not pour greater than
1.2 mt heigh. But if u are using hose pipe then u may cast
as per the lenth of hose pipe reaches in side of col,which
also maintains I.S. specification of 1.2 mtr heightpouring
Thus we can cast col. more then 1.2 mtr. height. Generaly
hose pipe may be inserted up to 2.0-2.5 mtr depth in col.
and we can cast up to 3.7 mtr height of col.
| Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
How to calculate ventonite bag in pile ( pile depth 25 m dia 1m)
1) write Short notes about Shellow & Deep well? 2) What is the full form of SPT & SMB? write short notes. 3) write short notes about efficiency of Riveted joint.
what energized you to complete your course?
A Cat excavator loader of 3Lm*3 heaped capacity bucket is to be used to load blasted rock directly into a crusher of capacity (consumption) of 100L
what is kribs is supporting?
How many litres of water used for curing of 1000sqft of slav
Explain the different types of building contracts?
what r the precaution for high in atp tempareture,low in atp tempareture
How many times we can use Fresh bentonite ford wall execution? Would like to know the clear concept of recycling. After flushing can we use it for another time time for flushing? Or we have to use it for for excavation only?
importance of the soundness test to determine the quality of cement use for any construction
Permissible wastage of cement as per IS code ? In which IS code I get it?
sir iam dng my engg final yr (civil) iam intrested to write group_1 .if we write this exam what kind of jobs we get and what should be the minimum score for us to get qualified and iam having reservation too.
If 40 backlogs are cleared m finally with 65 percent marks . Am I eligible to get visa to US
Explain what is change order request?
If we are providing concrete joint in every 10m with water stopper in water tank wall then is it necessary to cut the steel at joint section?