when you enter a po with item quantity 10 price RS.100/-.The
vendor sends an invoice with 15 quantity. NO GR.In real time
what you have done are you post the invoice.explain
Answer Posted / rajesh
If we required the additional 5 nos we can do GRN by giving
tolarence level to the material and post the GRN.
If tolerance level is not possiable take indent for another
5 Nos and amend the PO with 15 Nos and release it and then
do GRN for 15 Nos.
If we dont want the 5 Nos post the grn for 10 nos and send
back the 5 nos to vendor by raising the debit note against
the invoice.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
What are various procedures for counting physical inventory?
What do you mean by forecast-based planning?
Explain the types of consignement stocks in sap mm
What is the organizational structure in the mm module?
Where the schedule margin key is customized?
All Interview Question on SAP MM
What are the month end activities in sap mm?
What information is available in the 'accounting view' of a 'material master'?
Explain stock transfers?
Give some example of master data in material management (mm).
How are free items managed in a po? You need to tick the tem as free in the po. The price will be zero for such po's.
What is forecasting in sap system?
What is the differences between release procedure with classification and release procedure without classification? In which business scenario we use them?
What is the ‘price control indicator’?
How is consignment material procured?