If in a structure, e.g, 20mm steel bar is not available and
we use 16mm steel bar instead of 20mm bar, how can we
calculate the no. of steel bars for 16mm diameter bar?
Answer Posted / shailesh
In beam /column
Total cross section area of 20mm=total cross section area of
16mm
(3.14/4)*20*20=(3.14/4)*16*16*no
No=400/256
=1.56
| Is This Answer Correct ? | 31 Yes | 2 No |
Post New Answer View All Answers
How to do base isolation for RC framed structure using ETABS software?
is there any thumb rule for calculating construction cost of the building with pile foundation per sft. area?
Tell me about triple point of water.
how ratio is calculated for any grade of concrete. for e.g. sppose M20 requires(x;y:z) quantity of cememt sand and aggregate.
What are the joints wants to made in masonry where door opening, arches like etc..
pls give me some basic informations in construction of a structure?
What is kn measurement?
Why should pumping be not used in case of concreting works?
how to prepare site mix design
How to hide dimensions in autocad?
as per is code, what is the minimum content of opc and ppc cement for rcc structure
Why are separation membranes used between concrete pavement slab and sub-base?
manhole chamber having height of 2300 mm and thickness of brickwork is 230 mm and dia of opening covering is 560 mm and bottom length vertical is 1500 mm (1:4) brick masonry and plaster 12 mm on both sides..how to estimate the no bricks used with mortar cement bags and sand for total chamber including plaster.
In the design of bridge arguments what considerations should be made to select the orientation of the wing walls?
pls send me interview question paper with answer of EIL/AAI/UPSC/RPSC because i am doing prepration of compitation exam of UPSC for the Asst. Executive Engineer