what"s the formula to find the cement,sand,aggreegate(45mm)
requirement for PCC?
Answer Posted / shailesh
For 100 cum
Cement should be in kg=(152/sum of proportion)*cement density
Sand should be cum=(152/sum of proporation)*sand ratio
percentage
Aggregate shuid be in cum=(152/sum of proporation)*
percentage of aggreagate
For PCC 1:4:8 (100CUM)
Cement=(152/13)*1*1440=16836.92kg
Sand=(152/13)*446.769 cum
Aggregate=(152/13)*8=93.53cum
Is This Answer Correct ? | 16 Yes | 12 No |
Post New Answer View All Answers
Explain the benefits of using standard terminology in the measurement process?(Tendering and estimation)
Dear Engineers, Can you please advise me the material requirement to construct a room 4 M x 4 M 1. No. of Standard Brick 2. Requirement of Cement Bags 3. And Concrete for Steel, Cement, sand, etc Thanks
How to calculate the weight of sand am 20mm course aggregate in 1 c.m M25 concrete Which use 400 kg of cement ?
How to identify the vitrified tile and ceramic tile by observation only after executing the job.
what is that one cub metre plaster in cemant and fine sand
I'm preparing to to build a simple house, but i don't know how to calculate how much cement, gravel and sand and hollow blocks i need to prepare. How many pcs of 4" or 6" hollow blocks I need for my planned 3mx6m house? thanks.
What Are The Steps Involved In The Concreting Process, Explain?
Normally in slabs, steel quantity is not added when you calculating concrete quantity for that slab, why it is not added ?
Draw a neat sketch showing the 'throat' of a welding in a plate girder ?
How can I make justification between using concrete grade c35 compare c37?
what is tension footing?
how to calculate Rate of analysis for 100 m3 Any ratio of concrete ? including labour
what is diffrence between catchment area,watershed and basin?
How to hide dimensions in autocad?
What is difference between limit state and working stress method? How it is applies in building structure.