what"s the formula to find the quantity (consumption) of
cement,sand,aggregate for 1m3(1:2:4)?
Answer Posted / ajay kumar pal.(j.e)
for finding the total value of
take 1.52/(1+2+4)
=.22
hence total qty of cement .22*1= .22cum
cement= .22/.0354 = 6.2 bags of cement
sand = .22*2 = .44cum
Aggr =.22*4 =.88cum
ANS.
| Is This Answer Correct ? | 17 Yes | 6 No |
Post New Answer View All Answers
Any strength is a stress but any stress is not strength
roll of DLC in road constructions
psc girder detail
How to calculate chejja reinforcement
In block work seawalls what is the purpose of slip joints?
what isload waring calculation
What is 1/8 on the architect ruler denotes?
what is E
What is an object snap mode?
while doing the structural works of a simple ground+1 villa, can the columns be continued immediately after neck columns without tie beam, while the tie beam to be done after columns concreting.
what will happen if one could not properly follow the spacing of slab reinforcement bar?
the water is flowing through a velocity of 1.5m/s in a pipe of length 2500m and dia 500mm. at the end of pipe a valve is provided. find rise in pressure 1. if the valve is closed in 5 seconds. 2. if the valve is closed instantaneously. take value of c = 1460m/s, pipe to be rigid and bulk modulus of water - 19.692x10' n/sqcm
what is the proper procedure in conducting a california bearing ratio penetration test on soil on cbr machine?
how i get all type of short type question answer about civil engg
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.