How much kg of sand,cement will be for 1 sqmt(Blockwork-size 400x200x200)1:4 ratio & same for plaster
Answer Posted / harinath sharma
It's depend upon thickness of block work, if 4oo mm block
work then it's required 0.28 bag cement & 0.04 cuft sand.
for 200mm block work it's required .0106 bags cement,0.0147
cuft sand.
for plaster quantity depend thickness of plaster.
| Is This Answer Correct ? | 8 Yes | 0 No |
Post New Answer View All Answers
1. For 10sq.m area(47 kg bitumen contain) of 45 mm thick bitumen mix layer..how much bitumen is required for 1600 sq.m and how much aggregate need for that ?? 2. And much tonnage of bitumen mix required for 10 sq.m area of 45 mm thick. Please give answer...
What is the difference between built area and super built up area?
what is meant by shear center?????
how to identify np3 pipe and np4 pipe
What should be the lap length in raft if height of raft is 0.800mm ...it couldn't b 50D or 40D...we just have to join upper and bottom reinforced...is there any formula for determine it...
What is aggregate?
Which stone is best for wall construction Laterite Stone or Cement Blocks
How to calculate thickness of MAT slab & Reinforcement? The dimention of under ground water reservoir is 80'X14'X 12 ft
As per Kandal suggestions, we have implemented rolling starts on 140 (+/- 5) degrees and we kept 3 rollars to complete the rolling before falling 125 degrees and the Aggregate AIV is below 22. But When the DBM bed is being rolled 3rd high viabration, (Before 1 plain & low ,2 high Viabrations), the aggregate is getting sharp edge agg. projections are damaged. As the literature is said that, the VG-30 Grade having better control the temp. susceptibility than Penetration grade. if so we could not get this problem at site. But we are facing on site. let me know.
why are you joining in this (applied post) job and your aim for this job
What is the meaning of a blue land surveyors flag?
how to calclate the SHUTTERING TAKEN CONCRETE LOAD? WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE? WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE. PLATE SIZE IS 120CM* 90CM CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M PLS TO SENT THE CALCULATION.
what is the amount of absorption of slurry in shuttering ply board. what is the amount of slurry leakage allowed for 1 m3 of concrete.
suppose that 156000 sq.ft rcc work builtup are.how many % of brick work to rcc work.
Explain what are the skills required to become an architect?