Answer Posted / abdul hameed
Dear Instrumentation Friends,
The Loop checking is defined as pre-Commissioning activity
which is initiated after installation of instruments at x
location to y location instruments or systems.
Loop checking is basically done to ensure the instruments
installed at x and y location has continuity signal with
each other potential's.
If we want to loop check the continuity from instrument to
junction box this is acheieved by laying a cable between
instrument and jounction box.
Normally after installation and cable laying during
construction activity is to be ensured that instrument and
cable and junction termianls and cable which is layed
underground or above ground & is not damaged to confirm this
damage it is mandatory to carry out loop checking between
instruments-junction box- Dcs that is from field to control
room.
Simple Process:- is short the two cores of cable at one end
and check with digital multimeter at other end if the
circuit resistance is ok then the same cores have the cont
unity which means that the cable cores are'nt damaged.
above procedure also helps to identify the particular cable
cores for specific system founction
Above process is called as Cold Loop Checking loop checking
without any external sorce simulation.hencecalled as cold
loop check.
| Is This Answer Correct ? | 144 Yes | 15 No |
Post New Answer View All Answers
how to calibrate load cell
Instrumentation Safe Guarding test. How to determine the interval time of the test. eg:Halfyearly,Every year,Every three years etc.
What is standard of DCS panel design?and what is step of DCS panel design?wiring and type of connector(screw or DB connector)
WHAT ARE THE INSTRUMENTAL DIAGRAMSOF VALVES?
i have used level transmitter in starch cooking preparation tank. tank total height 2mtr.sometime LT display shows some error value when tank is fully empty and diaphragm side i already checked okay no problem in diaphragm area. field cable checked 24volt and mA shows correct value while tank empty mA is 4mA. 4mA i needed that 0% but display showing 10% or 15% percentage values are varying continously please give any good solution for me.....
Why upper weighing limit of electronics balance is 90% of the total weighing capacity?
How can test or measure the probe and extension cable to identify if the problem at the probe or cable or at the driver it self? (pleast notify the measuring method)
What is PDS and PDMS ?
Hi i am aneesh, done btech in applied electronics & instrumentatiin. And then i took mba in finance & marketing.After that i got placement in finance co and worked there for 3.5 yrs.Now i wanted to come back to engineering job.But without engg experience, i may not able to find an opening.i have done a course related to flow meters and ite calibrations. Kindly suggest where should i try to get a job?
detail of mass flow meter pricipal
when placing a vent or drain hole on an orifice plate should you measure from the center of the bore up or down for the vent placement?
I have 0.75mm sq multicore cable (IS type) , can use instead of same type but 1.5 sq mm cable ? Note : The distance is around about 150 meter.
How to calibrate RC Feeder system in thermal power station?,If any instrument available to calibrate it,ple inform me. make:stock,
I am teja. I am studying Msc(tech) Electronics and Instrumentation (3years course) in Andhra university. But my course is not recognised by UGC and AICTE. Please tell me the job opportunities after this course. And i fineshed PLC course in IGIAT ,Vizag.Also complted my short term coure in SCADA, Seimans WinCC in ATI,Hyd.After Msc can i join Mtech for good job? or phd. How i can get good job in INdustrial Automation Side. Please give replay.Because this is my life matter.
Sir, I want junior executive, Instrumentation question papaer for IOCL, Plz send to arabinda.ghosh83@gmail.com