how many m3, mason should done per day if he going to build
4.5 inch brick work(partition wall)?
Answer Posted / anil dhawan
Generally a mason can built maximum 10sqm half brick work
(with the help of 2 unskilled labour)per day.
so.its 10sqm(area)*.115(thk)=1.15 cum
| Is This Answer Correct ? | 6 Yes | 1 No |
Post New Answer View All Answers
Define relative co-ordinates?
what is the clear cover for shearwall?
What is the density of DLC & PQC and how it is differ from normal concrete?
how to estimate material requirement for an area of house in square feet?
What is the Hardness of M-40 grade concrete, general and theoratical
What Are The Steps Involved In The Concreting Process, Explain?
How many axes do cartesian coordinate system has?
show answer/calculate mix 1:2:4 ratio -cement-sand -metal-water
How do we determine the specific gravity of a cement?
I am doing a engineering contract with GOI. I have purchased certain material from outside Maharashtra and paid CST on that material @ 5.25%. Please intimate whether I will be liable for VAT or VAT on works contract or not.
what is meaning of inverted beam.is it way to provide double mat in slab one at bottom and another at topif we go for provision of inverted beam. shall we construct structure with out plinth beam for us we have to construct small bus shelter
As in practice, we are deducting every 2d for 90 degree bend but from where it comes means derivation or reference of IS Code.
A Cat excavator loader of 3Lm*3 heaped capacity bucket is to be used to load blasted rock directly into a crusher of capacity (consumption) of 100L
What is the Unit weight of coarse sand (F.M- 2.20) ?????
How to calculate plastering for elevated water storage tank