What is the method of Tan delta test for power Transformes
and why it is required.
Answer Posted / k.prakashchandra
The dissipation factor (tan delta) represents the gross
defects and overall dielectric losses in insulation.For this
an instrument(HV transformer ratio arm bridge) is available
for measurement of tan delta and capacitance.To assess the
state and quality of the mass of tr insulation ,the
following test schemes are used during measurement of tan
delta.1.HV vs LV grounded to tank 2.LV vs HV grounded to
tank 3.HV vs LV ungrounded 4.Bushing insulation with respect
to test tap.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
On what cycle does thermal power plant operate?
i need about 10 years of GATE solved papers in pdf format and even mock tests toooo
I had applied for JE in PSEB, Can you pls send me the Question bank for related to my field
Good morning: I'm looking for some informations about the OLTC or the LTC: I wont to know what the function of the tie-resistor in during the operation of reversing/coarse operation Cordially
can I improve the furnace power factor (10 mva transformer) by adding a capacitor bank before the transformer.Does system power factor vary a lot with the furnace PF?
what is method for testing CT
What we mean by vintage of an engine+Generator?
What is the lifetime of a Thyristor? Is there a recommended lifetime for thyristors after which they should be replaced?
what kinds of Transformer oil grade is better for power transformer ?
How to perform a DC resistance test In Alternator and their proceduces?
if you are in a software company,then why do you want to come in a core company like sail, ntpc(where lots of trouble like tension but you have a good life in a it company) ?
I have 4 busbar of 1000 ampere. we use 4 busbar to make 4000 ampere in one phase.my problem is that when we applied 60% load on that then busbar produced high noise.what is the reason of that and how can i minimize that noise.
WHAT CAUSED THRESHOLD VOLTAGE TO EXIST?
is it possible to test of bus bar in high rise building without completed full floor ?
What is the function of interposing current transformer?