what"s the formula to find the cement,sand,aggreegate(45mm)
requirement for PCC?

Answer Posted / vishnu soni

For 1 cum concrete 1:4:8, then we reqd following
quantities:-
1.54/sum of ratio
1.54/13= .11/.034=3.48 bags of cement
Fine Aggregate:-- .11x4=.44 cum
Coarse aggregate:-- .11x8=.88cum

Is This Answer Correct ?    55 Yes 18 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/

1358


How many square meter can mason layout chb per hour

1805


what are the Task work of different labour.?

2162


Anyone have sample questions for bhel interview.please send me as Iam appearing for the interview on 19th sep2008. Kindly send this to my e-mail: arun_prasath_n@yahoo.co.in

1600


what is cement wastage percentage in NHAI ROAD WORKS

1425






For the construction project what capital cost has to be taken in consideration?

674


whats is difference between anchorage length and development length

1374


trapozidal

2007


please briefly explain calculating or estimating steel quantity for a RCC column?

1443


How much cement and water required for cement selery????

1423


what is tension footing?

1534


how to calculate testing date

1235


how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend

1595


what is Quantity of stone and sand required for one cubic meter of stone work (UCR)

1642


If we buy crush sand for 3200/ Brass and cement for Rs350 /Bag and flyash 1200 / tonne....and my production is 230 Bricks per bag than how much cost is required for 1 flyash brick?

1712