I Have concrete mix with 440kg opc and having 37 mpa
strengh in 7days while in 28 days only 42mpa can anybody
tell me the reason for the same.
Answer Posted / imran
The reason behind this is that
on an average a concrete
attains 70 to 80%
compressive strength in 7
days whereas more than 90%
strength in 28 days
| Is This Answer Correct ? | 19 Yes | 1 No |
Post New Answer View All Answers
How to calculate the load of partion in flat slab if we use brick?
Define What does civil status mean?
what is work of planning deptt. in any construction compny (in road project)
brickwork labour rate per cum ?
what is E
How to calculate chejja reinforcement
What should be the lap length in raft if height of raft is 0.800mm ...it couldn't b 50D or 40D...we just have to join upper and bottom reinforced...is there any formula for determine it...
Before casting a basement roof slab which is connected with retaining wall surcharge load (i.e. sand or earth filling) outside the retaining wall is prohibited because of––
How much of the strength of concrete comes from post- production curing?
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .
How much quantity of cement and sand required for the inlining of 610mm dia MS pipe 8.7mm thk.Inlining thickness is 10mm and CM ratio is 1:1.5.
what does the grad of cement shows (denotes)?
what is w/c ratio in dry lean concrete for m10 mix design
What is missing report and how to prepare
The definition of national highway