Answer Posted / gurunath khavanekar
Stressing is the word generelly use in post-tentioning
slab.(PT slab)
stressing means stress the strands(cables) by using the
hydrulic machine. when the concrete get required strength.
| Is This Answer Correct ? | 19 Yes | 0 No |
Post New Answer View All Answers
why the openings of sieves are square io size?
find the discharge of water through a horizental venturimeter having 400mm dia at the inlet main and 150mm dia at thorat.if the diffrential gauge between inlet and thorat shows a pressure head of 25cm mercury. assume coefficient discharge 0.98 and specfic gravity of mercury as 13.6.
How much quantity of cement,sand,stone used to build 1 cum of cc road??
What do we mean by partial moment release ??
In csae of hume pipes NP stands for Non Pressure bur what does it really mean?
What materials were used to build the golden gate bridge?
3. What are the disadvantages of your present job, things you do not like about it?
by which materials we can prepare circular shuttering with tentative cost of material(rate analysis)
within an emergency scenario what are the safe systems of work a coss can setup as part of is duties
why building got air crack? if it get in one particular are what is means?
how much deduction will be in 32 mm dia HYSD steel bar for 45 and 90 degree bend
when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?
What are the main reasons for conducting pull-out tests for soil nails?
What are the RISKS during the project construction?
where will be the reinforcement of slab placed when there is an inverted beam and the bottom of the beam and slab are at same level ?