Answer Posted / v.kannan
while joining of new roof slab to existing one you should
ensure whether existing roof having reinforcement projection
for joining or not to new reinforcement. if not you want to
remove the concrete up to 150-300 mm from the edge and clean
the surfaces and existing bar then connect the new one and
we can make the concrete through proper form work. and the
grade of the concrete should not less than M25
| Is This Answer Correct ? | 29 Yes | 7 No |
Post New Answer View All Answers
What is Refuse Area In High Rise Building ?
How much cum. Brick work can do by 1 madon
What are the types of slump?
silt%= silt volume/ silt+sand volume is this right?
How do you compute the volume of airflow?
Detection of a beam & a girder areββββ
Define What is the best type of wood glue?
What is an object snap mode?
what is grade intersection?
what r the precaution for high in atp tempareture,low in atp tempareture
How foundation is designed, Column design and beam design
What is the method of soil replacement test?
How its coming concrete grade M 20 means 1:2:4. how it coming 1:2:4.
If 40 backlogs are cleared m finally with 65 percent marks . Am I eligible to get visa to US
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?