hi frienda We have 250kva cater pillet dg set we are fasing
one diffrent proublam in dg we are start dg set after one
mint applying load around 450a load but dg was run 3 Or 4
mints after 3 mints dg was shuding down automatic how to
face this proublam pls tel any budy
Answer Posted / ajay
that is 250kva d.g.it will be give only 250-300amps
load...you will also give to 300a load and then check it
OR
hydrollic magnatising is very low,d.g.will run there
after voltage is not buildup,then d.g.is shuting down...
please do one thing short your battery
terminals and then give to connection it will be started.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
How much depth n width required for laying of 1X70 Sqmm Cable in Desert???
PLS SEND THE RRB CHENNAI MODEL QUESTION PAPER my email id is ganesan98655@rediffmail.com
when ID fan will immediately stop through VFD what exactly cause and problem the ID fan
do anyone out there know where to find a compleete list on acronyms/abbreviations used in offshore electric engineering. MCB - Micro Circuit Breaker, MCCB-Mouldes Case Circuit Breaker, ELCB-Earth Lekage Circuit Breaker, ELMCB- etc.....
2. What are the parameters of EHT sub-station?
what are the factors to be considered while design the breaker either HT or LT??
how to deside the capacity of chock for drive?
what is the standard duration after failure EB power
is it possible to turn on the single phase star delta on delay timer using 24 v dc ?
In what condition the HT fuse breakes?
how to size H.T & L.T Panel ?
Explain Active power,reactive power,how its related to each other , & inductive ,capacitive.
by using pump duty, how we will can calculate the motor duty(KW)? is there any standard or formula.
How can get elongation of 2 k.G aluminium, if elongated aluminium dia is 2.5 mm?
why do we need to use 3c+3e cable, normally i select only 3c+e cable and i think it is enough. pls explain the usefull of 3e cable ( in this project the earthing system is well done)