how many area req.in 15000liter water tank

Answer Posted / m ghailani

15000 ltr.= 15 m3 (1 m3 =1000 ltr.)

For tank height = 1m +0.1m (free board)=1.1m
Area needed = 15m3/ 1m= 15m2

For tank height = 2m +0.1m (free board)=2.1m
Area needed = 15m3/ 2m= 7.5m2

similarly we can find the area for any depth.
note:Free board is the space to be left above water
(between water surface and tank cover), it is usually taken
as 10cm (0.1m).

Is This Answer Correct ?    1 Yes 4 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

how to diffenentiate the fixed beam and simply supported beam in the execution while reading the drawing and how the reinforcement detail will be differ for the above.

1964


Pls explain me about tension and compression in a flat slab

1589


Spider cracks occur in beam bottom due to––

1649


What materials were used to build the golden gate bridge?

812


HOw much % of premium on DSR-2013 currently

1538






1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.

1685


in plate load test what is the thickness of plate 20mm 5mm 50mm none

1710


How much sand and cement requirement for 1 SQM 125mm thickness Brickwork

303


construction workers how much time take one work or qty

1127


what's the formula for calculate pcc for matt(45mm aggregate)?

2159


what is meant by csr in foundation? what is sbc?what is meant by contour line?

1828


Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?

1646


Sir how to find cutting length for footing steel bars in the shape of "u"

1319


What is thumb rule in quantity and cost estimation of a residential building?

2643


trapozidal

2003