Answer Posted / paul
"Line Trap" are used on old HV networks, they are fitted for the interception of inter-trip signals between two connected substations.
The new method is to have a digital communication channel between the substations so the protection at both ends are constantly communicating with each other
Yes the "Line Trap" on each protected circuit has its own tuned frequency.
| Is This Answer Correct ? | 6 Yes | 1 No |
Post New Answer View All Answers
Keywords: Die, Card, Coin, B/N 2 To 12
What is q factor?
Testing report of Earthing of 3.15 MVa PTR.
what are the condition that makes hooter blow?
what happen as when voltage drop(or may decrease) ? in case of atomic base theory?
7- What is the Dissipation Factor and the difference between it and Insulation Resistance Test? 8- What is the task (function) of DC and AC reactors in power plant? 9- What is the task (function) of (open delta with earthed) in some types in transformers? 10- What is the base of the selection of the vector group in transformers? 11- What is the zig-zag transformer and its function by drawing in large detail? 12- What is the polarity ? 13- Why we make short between phase(R) in high side and phase (r) in low side in vector group test? Where High Side ( R ,S and T ) and Low Side ( r ,s and t ). 14- What are the time on delay and time off delay? 15- What is the vector group? 15- What is the task (function) of different types of vector group such as Dyn11 , Dd0 , YNd1,……..,?
what is the formula for hv test for cable and circuit breaker..????
What are the special cables required for explosion proof wiring?
what is reactive power?, why its measured in VA ? is it transient behavior of system?
how to synchronize 3 phase slip ring induction motors of different ratings.
Hello everyone, somebody knows what is a "surplice power" ? The hole phrase is: "This rating is appropriate for a generator set paralleled with an infinite bus e.g. a national electrical supply network or grid where the generator set is run at 100% load, 24 hours a day, 365 days a year and any surplice power is exported into the grid" Thanks in advance.
In our factory so many iron pillors are exists for supporting the shed/Hangar. If do more no of earthings at one piller instead of doing more earth pits in many locations and running earth strip around the hanger, I can save the money. Please suggest this method is acceptable as per Is specifications though the Earth resitance of the farthest piller is with in the limits as per IS specifications.
Briefly define and explain the following different types of Pulse Amplitude Modulation (PAM) with some examples. i) 2-PAM ii) 4-PAM iii) 8-PAM iv) 16-PAM v) Quadrature Amplitude Modulation (QAM)
What is inrush current? how can calculateit? what is the affect of it?
Where voltage are high and current to be interrupted is low the breaker preferred is: