how much quantity of tile placing can be finished by one mason
per day?
Answer Posted / yaswanth kumar
160 to 180 Sft/mason/day
| Is This Answer Correct ? | 42 Yes | 15 No |
Post New Answer View All Answers
Define What is Civil Engineering?
How much cement and sand required for 9"brick wall per square metre
Does VDF add strength to the flooring apart from preventing water ingress?
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
What is absolute pressure? How absolute pressure is calculated?
What is meant by dimensioning?
What is the Roll of Water Bonding under VDF road?
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
Which percentage of carpet area use in plot area of office building.
how to take concrete quantity for precast segment for viaduct project?
Define What materials were used to build the Golden Gate Bridge?
Explain the difference between shear and tensile strength.
IS code for grade of concrete for bamboo lintel????
how to calculate the chair reinforcement length in slabs, footing or anywhere??
How much cement and water required for cement selery????